We are fully down for a subset of customers. We're investigating the issue, and are rolling back a deployment.

US · App, US · API, US · Mobile

Inicio informado: 02/09/2026 · 12:08Última actualización del proveedor: 04/09/2026 · 13:53

Última consulta de PULSO: 26/11/2026 · 21:40 · Ciudad de México


Incident: An internal system responsible for automatically scaling backend server capacity in one of our compute clusters stopped replacing capacity that had been cycled out during routine maintenance. This caused a gradual reduction in available capacity over several hours. A subsequent deployment was activated with insufficient capacity, causing all new requests for that compute cluster to fail. To mitigate the impact, we reverted to a previous release revision, which still had sufficient capacity. Impact: For approximately 30 minutes, customers whose traffic was handled by this compute cluster saw full downtime; other customers were unaffected. No customer data was lost. Moving forward: We have added additional monitoring to detect this type of capacity-scaling failure much earlier, and have added safeguards to prevent deployments from shifting traffic before sufficient healthy capacity is confirmed. _Our metric considers a weighted average of uptime experienced by users at each data center. The number of minutes of downtime shown reflects this weighted average._

Texto del proveedor, en su idioma original. Puede describir solo parte del servicio.

Abrir fuente oficial ↗

Cronología · más reciente primero

  • Informe final

    Incident: An internal system responsible for automatically scaling backend server capacity in one of our compute clusters stopped replacing capacity that had been cycled out during routine maintenance. This caused a gradual reduction in available capacity over several hours. A subsequent deployment was activated with insufficient capacity, causing all new requests for that compute cluster to fail. To mitigate the impact, we reverted to a previous release revision, which still had sufficient capacity. Impact: For approximately 30 minutes, customers whose traffic was handled by this compute cluster saw full downtime; other customers were unaffected. No customer data was lost. Moving forward: We have added additional monitoring to detect this type of capacity-scaling failure much earlier, and have added safeguards to prevent deployments from shifting traffic before sufficient healthy capacity is confirmed. _Our metric considers a weighted average of uptime experienced by users at each data center. The number of minutes of downtime shown reflects this weighted average._
  • Resuelto

    This incident has been resolved.
  • En monitoreo

    A fix has been implemented and we are monitoring the results.
  • En investigación

    The rollback seems to have completely resolved errors. We're monitoring closely, but users should be able to access Asana again.
  • En investigación

    We are continuing to investigate this issue.
  • En investigación

    We are currently investigating this issue.