Resuelto

(Status: Resolved) Performance degradation been identified - PIT

Boyers, USA (PIT)

Inicio informado: 29/09/2026 · 09:23Última actualización del proveedor: 29/09/2026 · 13:49

Última consulta de PULSO: 27/11/2026 · 08:25 · Ciudad de México


Hyland has remediated the performance degradation issue. Recovery operations are continuing and no customer impact is expected. If any issues arise please please contact your first line of Hyland support.

Texto del proveedor, en su idioma original. Puede describir solo parte del servicio.

Abrir fuente oficial ↗

Cronología · más reciente primero

  • Resuelto

    Hyland has remediated the performance degradation issue. Recovery operations are continuing and no customer impact is expected. If any issues arise please please contact your first line of Hyland support.
  • En monitoreo

    A fix has been implemented and we are monitoring the results.
  • Identificado

    We are continuing to work on a fix for this issue.
  • Identificado

    Hyland has identified the issue and is continuing to take steps towards remediating the issue with the highest priority. Hyland will continue to post updates as they are available.
  • Identificado

    Hyland has identified the issue and are still working on the remediation with the highest priority. Additional details will be provided as they become available.
  • En investigación

    Hyland is aware of performance degradation in the PIT data center. Hyland is engaged and investigating this issue with the highest priority. Additional details will be provided as they become available.